Projects for 2009 year – boiler plants, heat and gas supply networks, water supply

Brief projects outline
In the course of its activity the Institute has gained extensive design work experience in construction of engineering infrastructure networks and power facilities at a wide range of locations.
Design documentation developed by the specialists of the Engineering Infrastructure Design Institute became the basis for construction and reconstruction of many facilities in the Russian Federation among which motorways, mainline and distribution gas and oil pipelines in the Central, North-West, Southern, Volga regions; heating networks, communications and telephony, power networks as well as water supply and sewerage networks of Moscow, Saint-Petersburg and Leningrad's area.
Our company designing the systems of electrochemical protection of underground utilities has provided protection of many tens of kilometers of underground utilities.
On the basis of drawn-up and approved by industrial safety expert review documentation on liquidation and preservation of hazardous production facilities hundreds of technical devices were decommissioned and excluded from the register.

Company projects — 2009

projects
2008

projects
2010

projects
2011

projects
2012

projects
2013

projects
2014

projects
2015

  1. Development of design and estimate documentation for the project: «Administrative Building of Arbitrary Court of the City of St. Petersburg and Leningrad Region.» Location: St. Petersburg, Smolnogo Street, 6 A: — external off-site power supply network, including design of transformer substation
    — external off-site heat supply network
    — external off-site water supply and sewage network
    — external off-site communication network
    — freeing the construction site from gas supply facilities
    — external distribution lines of wire broadcasting network

  2. Development of work project for reconstruction of district heat supply networks for State Unitary Enterprise «Fuel and Energy Complex of St. Petersburg» (GUP «TEK SPb»), 5630 m, for Quarter 6 in Krasnoye Selo.
  3. Design project for liquidation of hazardous production facility — fuel oil pump and chimney stack of boiler house. Location: St. Petersburg, Petrodvoretz, Zayachy Lane, 3.
  4. Works on development of design documentation for external gas pipeline, external water supply and sewage network, power supply network for the facility. Location: St. Petersburg, Petrogradsky District, Bokovaya Alley, 11 E.
  5. Installation of two Lamborghini boilers and development of design documentation for installation of 4 gas powered electrical generators MTP-100/150 for heat and power supply of production and storage complex. Location: St. Petersburg, Magnitogorskaya St, 11
  6. Development of documentation for correction of work project for capital repair of the facility «Khersonskaya Street from Bakunina Street to Sinopskaya Embankment»
  7. Estimation of natural gas demand for production and storage complex. Location: St. Petersburg, Magnitogorskaya St, 11..
  8. Development of design documentation «Arrangement of access from motorway «Approach to the Town of Gatchina» and exit from A-120 motorway (km 64+700 on the left) to the territory of storage terminal and roadside service»
  9. Development of work project of heat supply network and design project section «Corrosion Protection» for heat supply network of residential complex. Location: St. Petersburg, Petrogradsky District, Glukhaya Zelenina St, 4A.
  10. Development of design project for reconstruction of gas pipeline electrochemical protection units. Location: M-20 motorway «St. Petersburg – Pskov – Pustoshka – Nevel» to the border of the Republic of Belarus»
  11. Development of design documentation for gas boiler plant, gas supply and heat supply networks for the Southern Customs Administration Regional Canine Center. Location: Republic of Adygeya, Maikop, Quarter П-9, Podgornaya St, 405
  12. Structural analysis of steam ducts of the boiler plant using START software. Location: St. Petersburg, Salova St, 72 A
  13. Design project for liquidation of hazardous production facility – boiler plant and chimney stack. Location: St. Petersburg, Kurortny District, Ushkovo Village, Primorskoye Shosse, 611
  14. Design project for liquidation of hazardous production facilities – equipment of gas boiler plant and fuel oil farm of JSC «Sestroretsk Tool Works Factory». Location: St. Petersburg, Kurortny District, Sestroretsk, Voskova St, 2.
  15. Design and installation of dual-cycle heat supply system with heating station of the steam backup boiler building and reconstruction of the existing heat supply system of steam backup boiler of "North-West Heat Power Plant" branch of JSC «INTER RAO UES».
  16. Development of work project for relocation of heat supply network from under the construction site and design project section «Corrosion Protection» of the heat supply network. Location: St. Petersburg, Institutsky Prospect, 16, Bldg. 1.
  17. Development of work project for relocation of heat supply network from under the construction site and design project section «Corrosion Protection» of the heat supply network. Location: St. Petersburg, Svetlanovsky Prospect, 15 A.
  18. State contract for design of relaying the external sewage network for St. Petersburg State Institution for Additional Education of Children «Athletic Club bearing the name of V.F. Kraevsky».
  19. Development of design project for liquidation of hazardous production facility – external and internal gas pipeline for boiler plant of JSC MAGNETON Factory. Location: St. Petersburg, Kurchatova St, 9
  20. Delivery of design works for reconstruction of gas pipeline and oil product pipelines during reconstruction of A-229 motorway «Kaliningrad – Chernyakhovsk – Nesterov» to the border of the Republic of Lithuania.
  21. Design project for liquidation of hazardous production facility – gas boiler plant. Location: St. Petersburg, Bolshaya Ozernaya St, 84
  22. Development of work project for reconstruction of district heat supply network (6030 m), Quarter 24 North of Novoselov Street (СУН) of GUP «TEK SPb» heat supply area.
  23. Development of design project for liquidation of hazardous production facility – gas boiler plant. Location: St. Petersburg, Primorsky Prospect, 52
  24. Work project for rebuilding of external mean pressure gas pipeline and the electrochemical protection unit of the facility pipeline. Location: St. Petersburg, Primorsky Prospect, 52
  25. Development of validation for St. Petersburg Governmental Rule (centralization of issue of technical specifications for electrochemical protection of underground networks in St. Petersburg)
  26. Development of work project section «Corrosion Protection» for heat supply network. Location: St. Petersburg, Kosmonavtov Prospect, 63
  27. Development of design project for correction of horizontal and vertical position of Bakunina Prospect from Ispolkomskaya St to 2nd Sovetskaya St (including intersections of Bakunina Prospect with Ispolkomskaya St and 2nd Sovetskaya St)
  28. Execution of work project for reconstruction of trolleybus overhead contact line. Location: St. Petersburg, Belgradskaya St from Salova St to Slavy Prospect.
  29. Execution of work project for dismantling of trolleybus overhead contact line masts. Location: St. Petersburg, John Reed St from Badaeva St to Kollontay St.
  30. Development of design and estimate documentation for reconstruction of gas pipeline electrochemical protection units. Location: St. Petersburg, Ryabovskoe Road from Irinovsky Prospect to Kokhanovsky Lane

Projects 2017

Projects 2016

The year 2016 was quite difficult as for design branch in Russia in general, and for our organization in particular. Because of the general reduction of amount of works on design we have concluded only 31 contracts which main share - state.
Because of bad investment climate and economic sanctions the share of contracts with the developer companies was extremely insignificant.
This fact, and also economic events in Russia, became a reason for acceptance by our company "strategy of reduction of expenses" for the purpose of preservation of the leading engineering staff of experts, and deduction of positions in the design market.

Projects 2015

Despite a difficult economic situation in the country, 2015 was quite successful for our company. 48 new contracts were signed, and the share of the state and municipal contracts became much more, than in previous years.
It is explained by the general economic recession in Russia as a result of which many investment projects were stopped while implementation of address programs went under the voted budget.
Road design, development of project and working documentation on construction of water-heating boiler rooms, and also liquidation of hazardous production facilities in the different cities of our country such as: St. Petersburg, Apatity, Ufa, Kazan, Yekaterinburg, Krasnoyarsk, Arkhangelsk etc., became the main direction, in design and exploration work of our company in 2015.

Projects 2014

To summarize 2014, we can say that the direction vector of our activities and assigned work priorities selected by the company in 2012 are completely justified. 61 agreements and state contracts were signed with contractors by the Engineering Infrastructure Design Institute. Among our new partners are such large organizations as OJSC ALROSA-Gaz and FSBI Petersburg Nuclear Physics Institute named after B. P. Konstantinov. Almost the third part of the signed agreements is state contracts. This is a measure of complex execution of works by the specialists of our Institute, our competitive power and confidence placed to us on the part of the state organizations and institutes. And numerous favourable conclusions of the expertise of design and estimate documentation are the evidence of our qualification.

Projects 2013

75 new projects of state and investment financing are the result of the activities of our company for 2013. 2013 shows that the decisions made by us in the previous years and analysis of the Institute development prospects are true. Following this policy, we obtained new possibilities on the market of the design works and showed ourselves to good advantage both among private customers and in the district authorities of the Leningrad and Moscow Regions.

Projects 2012

For the Design Institute, 2012 is the year of discovery and deployment of new trends – out company has been authorized for work package on engineering surveys (topographical, geological engineering, engineering-ecological surveys, etc.) and also our Institute has been awarded the certificates of conformity of the ISO 9001-2008 quality management at development of design documentation and survey works.
A separate group of specialists on road engineering has been formed, by virtue of which the solution on new construction and reconstruction of motor roads in St. Petersburg, Leningrad Region and Naro-Fominsk are implemented.
In 2012 the Engineering Infrastructure Design Institute concluded 90 investment contracts and state contracts and in this connection the works are performed.

Projects 2011

In 2011 our company implemented 60 large projects in different regions of Russia. Our main customers were legal entities and enterprises of JSC INTER RAO UES. New direction on survey, calculation and installation of hanger-support pipeline system was launched in the Design Institute.

Projects 2010

In the year 2010 the Engineering Infrastructure Design Institute has entered into and is performing works under 58 agreements and contracts. In most cases, the projects are owned by investment and developer companies. The Institute has also broadened the geography of its activities, working at facilities in Western Siberia.

Projects 2009

In the year 2009 the Institute specialists completed design works under 34 private commercial and federal contracts. Almost all design project documentation received the necessary approvals in expert and sanctioning organizations and was passed on to be applied for construction and installation works. Company employees built 3 heat power facilities completing full work cycle from design and survey works to commissioning.

Projects 2008

Within the period from June till December 2008 the company implemented 19 package design contracts.
Main assignment – design of linear facilities during modernization of motor roads, design of electrochemical protection installations for underground pipelines.